Opening the form
Open the form by right-clicking in the Industry Model Explorer under Data Model > Planning Result > Resulting Duct
or
by double-clicking on the result duct geometry in the graphic window.
Attributes
Phase
At the Result: Resulting Duct we find the Phase attribute of the rollout phase area where the duct is located.
Deployment
YES > the element will be built immediately.
NO > the element will be built at a later stage.
The Deployment attribute is filled depending on the Connection Type attribute at the demand point.
References
The resulting duct has a link with the input duct attribute if it is a result from an input / existing duct.
The subordinate ducts and cables are displayed in the lower left window.
The name “Duct Type” is taken from the duct identifier of the optimizer settings in the corresponding layers.
The “Duct Type” defines whether it is a single duct, a conventional duct, or a Microduct Bundles.